Update as of 2/23/2018

 

The last fire hydrant is being replaced on (2/26/18).  Landscape restoration will commence next week.  The final anticipated completion date for all associated work remains March 8, 2018.  

 

HYDRANT REPLACEMENT SUMMARY/BACKGROUND INFORMATION - Posted on 2/5/2018

 

In FY 17, three non-functional fire hydrants along the west side of SR A1A were replaced as part of the water main replacement project.  This year the Commission approved funding for the replacement of the remaining eleven fire hydrant assemblies along the west side of SR A1A as they are obsolete and have exceeded their useful service life.

 

Last month, Man Con, Inc., the contractor who performed the side street water main replacement project, was awarded a contract by the Town Commission to supply and install the above-referenced hydrant assemblies.  Furthermore, Mathews Consulting, the firm who designed the improvements has been retained to perform construction management services for the duration of this project.

 

The Hydrant Replacement Project is due to commence on February 6, 2018 and expected to conclude in March barring any delays caused by unforeseen circumstances.  A tentative schedule, including work locations, has been provided herein. 

 

While the contractor will endeavor to minimize any disruptions to pedestrian, bicycle and traffic flow, it will be necessary to periodically close off limited sections of the walk path in order to replace these fire hydrant assemblies.  The Town is asking for the cooperation from our walk path users to observe and obey signs, barricades, cones and other control devices that may deployed in these areas in the interest of public safety.  While there may be some temporary and hopefully minor inconveniences, it is all for the long-term good of the community as the new hydrants will enhance fire suppression capabilities, improve the water main distribution system flushing program, and is representative of the Commission’s Commitment to infrastructure re-investment.

 

HIGHLAND BEACH SR A1A WEST SIDE HYDRANT REPLACEMENT PROJECT

TENTATIVE CONSTRUCTION SCHEDULE

 

The Contractor (Man Con, Inc.) intends to begin on the South end of Town on Tuesday, February 6, 2018 and will progress northward along SR A1A until the project (the replacement of 11 hydrants) is complete.  The tentative work schedule is as follows:

 

  DATE STREET ADDRESS APPROXIMATE LOCATION
1 February 6, 2018 4758 S. Ocean Blvd. South End of Milani Park
2 February 7, 2018 4600 S. Ocean Blvd. Near Carron House
3 February 8, 2018 3719 S. Ocean Blvd. 10’ North of Toscana Entry
4 February 9, 2018 3620 S. Ocean Blvd. 10’ South of Ocean Grande Entry
5 February 12, 2018 3614 S. Ocean Blvd. Front of Town Hall
6 February 13, 2018 3312 S. Ocean Blvd. Between Seagate/Villa Costa
7 February 14, 2018 3210 S. Ocean Blvd. Near Villa Costa
8 February 15, 2018 3012 S. Ocean Blvd. Edgewater Town Houses
9 February 16, 2018 2912 S. Ocean Blvd. Across  SR A1A from Trafalgar
10 February 20, 2018 Boat Docks Across SR A1A from Villa Magna
11 February 21, 2018 2366 S. Ocean Blvd. Private Residence
February 21 – 28, 2018: Restoration of Landscaping
March 1 – 7, 2018: Walk-through & Punch List
March 8, 2018: Final Completion

 

Please note that this is a tentative schedule and may be subject to change without notice due to weather, emergencies or other unforeseen circumstances.  An announcement will be made as soon as possible if any of these conditions results in a deviation from the proposed timeline.   Should you have any questions, please feel free to contact the Public Works Department at 561-243-2084.